nerdexam
Scaled_Agile

SAFE-RTE · Question #59

The team's draft plan review consists of which three items at the end of the first day of the Program Increment (PI) Planning event? (Choose three.)

The correct answer is A. Capacity and load estimates C. Draft PI Objectives D. Risks and impediments. See the full explanation below for the reasoning.

Question

The team's draft plan review consists of which three items at the end of the first day of the Program Increment (PI) Planning event? (Choose three.)

Options

  • ACapacity and load estimates
  • BProgram delivery schedule
  • CDraft PI Objectives
  • DRisks and impediments
  • EIteration Goals
  • FRefined team backlogs

How the community answered

(32 responses)
  • A
    75% (24)
  • B
    16% (5)
  • E
    3% (1)
  • F
    6% (2)

Community Discussion

No community discussion yet for this question.

Full SAFE-RTE Practice