The correct answer is C. Prior to iteration planning. See the full explanation below for the reasoning.

Question

When should a Product Owner (PO) develop preliminary Iteration Goals?

Options

  • AAfter PI Planning
  • BDuring PI Planning
  • CPrior to iteration planning
  • DDuring backlog refinement