The correct answer is C. Prior to iteration planning. See the full explanation below for the reasoning.
Question
When should a Product Owner (PO) develop preliminary Iteration Goals?
Options
- AAfter PI Planning
- BDuring PI Planning
- CPrior to iteration planning
- DDuring backlog refinement