SAFE-RTE · Question #54
During the management review and problem-solving meeting, one team raises the risk of not finishing a Feature before the end of the Program Increment (PI). How can the man-agement team help ensure…
The correct answer is D. Negotiate a reduction in scope of the Feature. See the full explanation below for the reasoning.
Question
During the management review and problem-solving meeting, one team raises the risk of not finishing a Feature before the end of the Program Increment (PI). How can the man-agement team help ensure they complete the Feature within the PI?
Options
- AUse buffer resources as a guard band
- BRedefine the definition of done for Features
- CROAM the risk appropriately
- DNegotiate a reduction in scope of the Feature
How the community answered
(28 responses)- A18% (5)
- B7% (2)
- C4% (1)
- D71% (20)
Community Discussion