During the management review and problem-solving meeting, one team raises the risk of not finishing a Feature before the end of the Program Increment (PI). How can the man-agement team help ensure…

The correct answer is D. Negotiate a reduction in scope of the Feature. See the full explanation below for the reasoning.

Question

During the management review and problem-solving meeting, one team raises the risk of not finishing a Feature before the end of the Program Increment (PI). How can the man-agement team help ensure they complete the Feature within the PI?

Options

  • AUse buffer resources as a guard band
  • BRedefine the definition of done for Features
  • CROAM the risk appropriately
  • DNegotiate a reduction in scope of the Feature

How the community answered

(28 responses)
  • A
    18% (5)
  • B
    7% (2)
  • C
    4% (1)
  • D
    71% (20)