Scaled_Agile
SAFE-RTE · Question #37
When estimating stories, what is the Scrum Master's key responsibility?
The correct answer is B. Ensure everyone on the team participates. See the full explanation below for the reasoning.
Question
When estimating stories, what is the Scrum Master's key responsibility?
Options
- AEnsure the team gives accurate estimates
- BEnsure everyone on the team participates
- CProvide information about customer needs
- DLimit discussion to manage timeboxes
How the community answered
(48 responses)- A15% (7)
- B77% (37)
- C2% (1)
- D6% (3)
Community Discussion
No community discussion yet for this question.