SAFE-RTE · Question #3
Program Increment (PI) Planning is a major event that requires preparation, coordina-tion, and communication. What are two key areas a Release Train Engineer should focus on to support a successful…
The correct answer is A. Organizational readiness - Strategic alignment; roles, teams, and train setup D. Facilities readiness - Space and logistics for the event. See the full explanation below for the reasoning.
Question
Program Increment (PI) Planning is a major event that requires preparation, coordina-tion, and communication. What are two key areas a Release Train Engineer should focus on to support a successful PI Planning event? (Choose two.)
Options
- AOrganizational readiness - Strategic alignment; roles, teams, and train setup
- BArchitectural readiness - Defining the Architectural Runway
- COperational readiness - Facilitating PI events such as scrum of scrums, Iteration Planning, and
- DFacilities readiness - Space and logistics for the event
- EProcess readiness - The operational rhythm that enables SAFe governance
How the community answered
(33 responses)- A76% (25)
- B6% (2)
- C15% (5)
- E3% (1)