What is one way to secure stakeholder commitment to the Agile Release Train?

The correct answer is D. Have them attend the Program Increment (PI) Planning event. See the full explanation below for the reasoning.

Question

What is one way to secure stakeholder commitment to the Agile Release Train?

Options

  • AProvide them a planning schedule outlining a five-year plan for development
  • BHave them estimate User Stories for the teams
  • CSend them the Program Increment (PI) Objectives after each PI Planning event
  • DHave them attend the Program Increment (PI) Planning event

How the community answered

(21 responses)
  • A
    19% (4)
  • B
    5% (1)
  • C
    5% (1)
  • D
    71% (15)