Why is a confidence vote held at the end of program increment (Pl) planning?

The correct answer is A. To build shared commitment to the plan. See the full explanation below for the reasoning.

Question

Why is a confidence vote held at the end of program increment (Pl) planning?

Options

  • ATo build shared commitment to the plan
  • BTo remove the risks for the Pl
  • CTo ensure the business owners accept the plan
  • DTo hold the teams accountable if the Agile release train (ART) does not deliver on its commitment

How the community answered

(18 responses)
  • A
    78% (14)
  • B
    11% (2)
  • C
    6% (1)
  • D
    6% (1)