SAFE-RTE · Question #182
A feature planned for the current PI was not completed and a third of the work remains to be done. What should happen?
The correct answer is B. The remaining work needs to be estimated and that size is used in WSJF. See the full explanation below for the reasoning.
Question
A feature planned for the current PI was not completed and a third of the work remains to be done. What should happen?
Options
- AThe feature's original size estimate is used in Weighted Shortest Job First (WSJF)
- BThe remaining work needs to be estimated and that size is used in WSJF
- CThe sum of all story points for the feature is the size estimate used in WSJF
- DThe feature does not need to be scored in WSJF; it carries into the next PI automatically Answer
How the community answered
(42 responses)- A12% (5)
- B79% (33)
- C2% (1)
- D7% (3)