Which two activities take place during Team Breakout #1 on the first day of Program In-crement (PI) Planning? (Choose two.)

The correct answer is C. Draft objectives and uncommitted objectives are written D. All teams' planning boards are visible and use the same color-coding. See the full explanation below for the reasoning.

Question

Which two activities take place during Team Breakout #1 on the first day of Program In-crement (PI) Planning? (Choose two.)

Options

  • ARisks on the teams' planning boards are resolved by the Release Train Engineer
  • BTeams use color-coding for their backlog items as a reminder that they are re-quired to have all
  • CDraft objectives and uncommitted objectives are written
  • DAll teams' planning boards are visible and use the same color-coding
  • EDraft objectives are written but do not include exploration Enablers

How the community answered

(20 responses)
  • A
    5% (1)
  • B
    15% (3)
  • C
    75% (15)
  • E
    5% (1)

Community Discussion

No community discussion yet for this question.