Which two activities take place during Team Breakout #1 on the first day of Program In-crement (PI) Planning? (Choose two.)
The correct answer is C. Draft objectives and uncommitted objectives are written D. All teams' planning boards are visible and use the same color-coding. See the full explanation below for the reasoning.
Question
Which two activities take place during Team Breakout #1 on the first day of Program In-crement (PI) Planning? (Choose two.)
Options
- ARisks on the teams' planning boards are resolved by the Release Train Engineer
- BTeams use color-coding for their backlog items as a reminder that they are re-quired to have all
- CDraft objectives and uncommitted objectives are written
- DAll teams' planning boards are visible and use the same color-coding
- EDraft objectives are written but do not include exploration Enablers
How the community answered
(20 responses)- A5% (1)
- B15% (3)
- C75% (15)
- E5% (1)