What is a common reason why a team is unable to estimate a story?
The correct answer is B. The story lacks acceptance criteria. See the full explanation below for the reasoning.
Question
What is a common reason why a team is unable to estimate a story?
Options
- AThe team does not understand the tasks related to the story
- BThe story lacks acceptance criteria
- CThe team has no experience in estimating
- DThe story does not include a role
How the community answered
(42 responses)- A7% (3)
- B76% (32)
- C2% (1)
- D14% (6)