What is a strategy a Product Owner can use during Program Increment Planning to mini-mize dependencies?
The correct answer is B. Move Stories on their team's backlog to another team. See the full explanation below for the reasoning.
Question
What is a strategy a Product Owner can use during Program Increment Planning to mini-mize dependencies?
Options
- AChange the definition of done
- BMove Stories on their team's backlog to another team
- CReprioritize Epics
How the community answered
(37 responses)- A5% (2)
- B84% (31)
- C11% (4)