The correct answer is C. Decouple deployment from release E. Continuous Integration. See the full explanation below for the reasoning.
Question
Which two practices are most important for the Agile Release Train to best support Re-lease on Demand? (Choose two.)
Options
- AAligning around organizational value streams
- BCentralized risk management
- CDecouple deployment from release
- DChange board community of practice
- EContinuous Integration
Community Discussion