SAFE-RTE · Question #145

Which two practices are most important for the Agile Release Train to best support Re-lease on Demand? (Choose two.)

The correct answer is C. Decouple deployment from release E. Continuous Integration. See the full explanation below for the reasoning.

Question

Which two practices are most important for the Agile Release Train to best support Re-lease on Demand? (Choose two.)

Options

  • AAligning around organizational value streams
  • BCentralized risk management
  • CDecouple deployment from release
  • DChange board community of practice
  • EContinuous Integration

How the community answered

(43 responses)
  • A
    16% (7)
  • B
    2% (1)
  • C
    72% (31)
  • D
    9% (4)

Community Discussion

No community discussion yet for this question.