The correct answer is A. Coordinating with other teams. See the full explanation below for the reasoning.
Question
In SAFe, which activity is a Scrum Master's responsibility?
Options
- ACoordinating with other teams
- BOwning the daily stand-up
- CFacilitating the Scrum of Scrums
- DPrioritizing the Team Backlog