SAFE-RTE · Question #140

Which of the following is true about the ART sync event?

The correct answer is B. It is a combination of PO-sync and Scrum of Scrums events. See the full explanation below for the reasoning.

Question

Which of the following is true about the ART sync event?

Options

  • AIt is run after PO-sync and Scrum of Scrum events
  • BIt is a combination of PO-sync and Scrum of Scrums events
  • CIt occurs during the Innovation and Planning iteration
  • DAttendance by the entire ART is important

How the community answered

(22 responses)
  • A
    5% (1)
  • B
    77% (17)
  • C
    14% (3)
  • D
    5% (1)