Scaled_Agile
SAFE-RTE · Question #140
Which of the following is true about the ART sync event?
The correct answer is B. It is a combination of PO-sync and Scrum of Scrums events. See the full explanation below for the reasoning.
Question
Which of the following is true about the ART sync event?
Options
- AIt is run after PO-sync and Scrum of Scrum events
- BIt is a combination of PO-sync and Scrum of Scrums events
- CIt occurs during the Innovation and Planning iteration
- DAttendance by the entire ART is important
How the community answered
(22 responses)- A5% (1)
- B77% (17)
- C14% (3)
- D5% (1)
Community Discussion
No community discussion yet for this question.