The goal of Lean is to deliver the maximum customer value in the shortest sustainable lead time while providing what else?
The correct answer is A. The highest possible quality. See the full explanation below for the reasoning.
Question
The goal of Lean is to deliver the maximum customer value in the shortest sustainable lead time while providing what else?
Options
- AThe highest possible quality
- BA Continuous Delivery Pipeline
- CSignificant team contributions
- DImproved capacity allocation
How the community answered
(53 responses)- A81% (43)
- B11% (6)
- C6% (3)
- D2% (1)