Scaled_Agile
SAFE-RTE · Question #121
What should the Release Train Engineer do during the final plan review on Day two of Program Increment (PI) Planning?
The correct answer is D. Facilitate all teams when they are presenting their final plans to the entire Agile Release Train. See the full explanation below for the reasoning.
Question
What should the Release Train Engineer do during the final plan review on Day two of Program Increment (PI) Planning?
Options
- AEncourage discussion of each team's product Vision as part of the final plan re-view
- BVerify that each team's uncommitted objectives have lower business value than the committed PI
- CFacilitate the ROAMing of each team's risks
- DFacilitate all teams when they are presenting their final plans to the entire Agile Release Train
How the community answered
(21 responses)- A10% (2)
- B5% (1)
- D86% (18)
Community Discussion
No community discussion yet for this question.