Question
What should the Release Train Engineer do during the final plan review on Day two of Program Increment (PI) Planning?
Options
- AEncourage discussion of each team's product Vision as part of the final plan re-view
- BVerify that each team's uncommitted objectives have lower business value than the committed PI
- CFacilitate the ROAMing of each team's risks
- DFacilitate all teams when they are presenting their final plans to the entire Agile Release Train
Unlock SAFE-RTE to see the answer