SAFE-RTE · Question #113
When looking at a program board at the end of program increment (Pl) planning, what does it mean when a feature is placed in a team's swim lane with no strings?
The correct answer is A. That the feature can be completed by that team independently. See the full explanation below for the reasoning.
Question
When looking at a program board at the end of program increment (Pl) planning, what does it mean when a feature is placed in a team's swim lane with no strings?
Options
- AThat the feature can be completed by that team independently
- BThat the team has not broken the feature into stories yet and has not identified dependencies
- CThat it has dependencies on teams in other Agile release trains (ARTs) or Solution Trains
- DThat the team has been assigned, but the feature' u閜endencies have not been identified yet
How the community answered
(33 responses)- A79% (26)
- B12% (4)
- C3% (1)
- D6% (2)