When looking at a program board at the end of program increment (Pl) planning, what does it mean when a feature is placed in a team's swim lane with no strings?
Options
- AThat the feature can be completed by that team independently
- BThat the team has not broken the feature into stories yet and has not identified dependencies
- CThat it has dependencies on teams in other Agile release trains (ARTs) or Solution Trains
- DThat the team has been assigned, but the feature' u閜endencies have not been identified yet