At the end of day two of the Program Increment (PI) Planning event, the team's final plan review covers what information?

The correct answer is B. Changes to capacity and load, final PI objectives, program risks and impediments. See the full explanation below for the reasoning.

Question

At the end of day two of the Program Increment (PI) Planning event, the team's final plan review covers what information?

Options

  • ATeam Features, Stories, and team-level enablers
  • BChanges to capacity and load, final PI objectives, program risks and impediments
  • CChanges to iteration goals, measured velocity, and dependencies
  • DPlanned Features, uncommitted objectives, and ROAMed risks

How the community answered

(62 responses)
  • A
    15% (9)
  • B
    76% (47)
  • C
    3% (2)
  • D
    6% (4)