An R&D group director approves a major program's charter although the director has a high level of understanding of the program's scope (hoy are unsure of how the program manager can be successful…
The correct answer is A. Establish high-level program milestones. See the full explanation below for the reasoning.
Program Stakeholder Engagement
Question
An R&D group director approves a major program's charter although the director has a high level of understanding of the program's scope (hoy are unsure of how the program manager can be successful in delivering the program's commitments What should the program manager do to align stakeholders with planning and monitoring the program's progress?
Options
- AEstablish high-level program milestones
- BDevelop an accountability matrix, and assign program roles and responsibilities
- CGenerate a supplier management plan to identify external stakeholders
- DCreate a communications management plan, and establish reporting formats
How the community answered
(25 responses)- A72% (18)
- B8% (2)
- C16% (4)
- D4% (1)
Topics
#stakeholder alignment#program milestones#planning#progress monitoring