What is the OPTIMAL lime in the construction process for ICT submittals to be reviewed by the ICT distribution designer?
The correct answer is A. After the contract is awarded and before project close out. See the full explanation below for the reasoning.
ICT Design Process and Project Management
Question
What is the OPTIMAL lime in the construction process for ICT submittals to be reviewed by the ICT distribution designer?
Options
- AAfter the contract is awarded and before project close out
- BAs part of the contract bid process to prevent project delays
- CBefore the contract is awarded
- DAt the beginning of the close out process
How the community answered
(19 responses)- A84% (16)
- B11% (2)
- D5% (1)
Topics
#ICT submittals#construction process timeline#submittal review#project administration