When preparing an upfront cost estimate, the ICT distribution designer MUST consider which two of the following fees? (Select two options.)

Sign in or unlock RCDDV15 to reveal the answer and full explanation for question #35. The question stem and answer options stay visible for context.

ICT Design Process and Project Management

Question

When preparing an upfront cost estimate, the ICT distribution designer MUST consider which two of the following fees? (Select two options.)

Options

  • ATaxes
  • BPermits
  • CInspection
  • DLicensing
  • ESafety

Unlock RCDDV15 to see the answer

You've previewed enough free RCDDV15 questions. Unlock RCDDV15 for full answers, explanations, the timed quiz mode, progress tracking, and the master PDF. Question stem and options stay visible so you can still see what's on the exam.

Topics

#cost estimation#permits#inspection fees#project budgeting