When preparing an upfront cost estimate, the ICT distribution designer MUST consider which two of the following fees? (Select two options.)

The correct answer is B. Permits C. Inspection. See the full explanation below for the reasoning.

ICT Design Process and Project Management

Question

When preparing an upfront cost estimate, the ICT distribution designer MUST consider which two of the following fees? (Select two options.)

Options

  • ATaxes
  • BPermits
  • CInspection
  • DLicensing
  • ESafety

How the community answered

(45 responses)
  • A
    4% (2)
  • B
    78% (35)
  • D
    4% (2)
  • E
    13% (6)

Topics

#cost estimation#permits#inspection fees#project budgeting