Open RFI's should be reviewed on a _________basis.

The correct answer is C. weekly. See the full explanation below for the reasoning.

ICT Design Process and Project Management

Question

Open RFI's should be reviewed on a _________basis.

Options

  • Adaily
  • Bbi-weekly
  • Cweekly
  • Dbi-monthly

How the community answered

(47 responses)
  • A
    4% (2)
  • B
    6% (3)
  • C
    74% (35)
  • D
    15% (7)