RCDDV15 · Question #29
Open RFI's should be reviewed on a _________basis.
The correct answer is C. weekly. See the full explanation below for the reasoning.
ICT Design Process and Project Management
Question
Open RFI's should be reviewed on a _________basis.
Options
- Adaily
- Bbi-weekly
- Cweekly
- Dbi-monthly
How the community answered
(47 responses)- A4% (2)
- B6% (3)
- C74% (35)
- D15% (7)
Topics
#RFI management#construction administration#project documentation#issue tracking