In which phase of the protect design would an ICT distribution designer be expected to prepare preliminary cost estimates?
The correct answer is B. SD. See the full explanation below for the reasoning.
ICT Design Process and Project Management
Question
In which phase of the protect design would an ICT distribution designer be expected to prepare preliminary cost estimates?
Options
- ACD
- BSD
- CPD
- DDD
How the community answered
(25 responses)- A4% (1)
- B72% (18)
- C16% (4)
- D8% (2)
Topics
#design phases#schematic design#cost estimation#project lifecycle