The correct answer is A. The heat load (BTU (calories/hour) of all equipment installed within the space. See the full explanation below for the reasoning.
Question
Which requirement does the ICT distribution designer provide to the Mechanical Engineer in charge of the HVAC design for a Telecommunication Space?
Options
- AThe heat load (BTU (calories/hour) of all equipment installed within the space
- BLocation of the telecommunications own dedicated electrical distribution panel
- CThe quantity and size of HVAC vents needed for the room
- DLocation and size of condensate drain