RCDDV15 · Question #2
Which type of scheduling chart utilizes predecessor and successor relationships when identifying tasks?
The correct answer is A. PERT. See the full explanation below for the reasoning.
Project Management
Question
Which type of scheduling chart utilizes predecessor and successor relationships when identifying tasks?
Options
- APERT
- BCalendar
- CMilestone
- DGantt
How the community answered
(49 responses)- A82% (40)
- B10% (5)
- C6% (3)
- D2% (1)
Topics
#PERT chart#project scheduling#predecessor-successor relationships#project management