Which type of scheduling chart utilizes predecessor and successor relationships when identifying tasks?

The correct answer is A. PERT. See the full explanation below for the reasoning.

Project Management

Question

Which type of scheduling chart utilizes predecessor and successor relationships when identifying tasks?

Options

  • APERT
  • BCalendar
  • CMilestone
  • DGantt

How the community answered

(49 responses)
  • A
    82% (40)
  • B
    10% (5)
  • C
    6% (3)
  • D
    2% (1)

Topics

#PERT chart#project scheduling#predecessor-successor relationships#project management