When responding to a submittal that has been rejected and/or has comments written by a reviewer, the ICT distribution designer may need to perform which two of the following actions? (Select two…
The correct answer is D. Request a variance from the contract requirements from the client. E. Submit an alternate product in lieu of one that was previously submitted, even if it does not meet. See the full explanation below for the reasoning.
Project Management
Question
When responding to a submittal that has been rejected and/or has comments written by a reviewer, the ICT distribution designer may need to perform which two of the following actions? (Select two options.)
Options
- ARequest a Change Order from the client for the extra work performed.
- BDocument the reviewer's status and/or comments
- CReview the contract requirements and revise the submittal to comply with these requirements
- DRequest a variance from the contract requirements from the client.
- ESubmit an alternate product in lieu of one that was previously submitted, even if it does not meet
How the community answered
(33 responses)- A15% (5)
- B3% (1)
- C6% (2)
- D76% (25)
Topics