What is used to facilitate MINOR changes to the Project Requirements? Request lot Information (RFI)
The correct answer is C. Change order. See the full explanation below for the reasoning.
Project Management
Question
What is used to facilitate MINOR changes to the Project Requirements? Request lot Information (RFI)
Options
- APunch list
- BField order
- CChange order
- DChange order request
How the community answered
(23 responses)- A4% (1)
- B9% (2)
- C83% (19)
- D4% (1)
Topics
#change management#field order#project documentation#RFI