The correct answer is D. Attempt to call the key stakeholder, if unsuccessful, visit their office to identify potential risks. See the full explanation below for the reasoning.

Question

A component project manager escalates an issue regarding a key stakeholder to the program manager. The key stakeholder does not respond to emails or phone calls and the project manager believes this key stakeholder is exhibiting a negative attitude toward the work. The key stakeholder has a significant influence over the component project which could impact other components if delays occur. The program manager's attempts to reach the stakeholder via email also fail. What should the program manager do next?

Options

  • AEscalate the issue to the stakeholder's supervisor.
  • BEscalate the issue to the program governance board as delays will impact the program
  • CUpdate the program risk register to reflect a realized risk and execute the documented risk
  • DAttempt to call the key stakeholder, if unsuccessful, visit their office to identify potential risks