RCDDV15 · Question #182
The project manager of project A develops a communications management plan. The project manager of project B is new and is uncertain how to develop appropriate communications for the company's…
The correct answer is D. Rework the communications management plans for all projects to be consistent. See the full explanation below for the reasoning.
Program Stakeholder Engagement
Question
The project manager of project A develops a communications management plan. The project manager of project B is new and is uncertain how to develop appropriate communications for the company's staff. What should the program manager do to ensure communications on the component projects are consistent?
Options
- ARequest a more experienced project manager to work on project 6
- BCreate a program communications management plan across all component projects
- CDirect all projects to use project A's communications management plan as a template
- DRework the communications management plans for all projects to be consistent
How the community answered
(23 responses)- A13% (3)
- B4% (1)
- C4% (1)
- D78% (18)
Topics
#communications management plan#component project consistency#program manager role#stakeholder communications