RCDD-002 · Question #358

A document containing information that a contractor MUST provide to the design team for review and approval throughout a project's life cycle is called a

The correct answer is C. submittal. See the full explanation below for the reasoning.

Question

A document containing information that a contractor MUST provide to the design team for review and approval throughout a project’s life cycle is called a

Options

  • Awork breakdown structure (WBS).
  • Brequest for information (RFI).
  • Csubmittal.
  • Dnotice to proceed.

How the community answered

(38 responses)
  • A
    8% (3)
  • B
    18% (7)
  • C
    71% (27)
  • D
    3% (1)