A document containing information that a contractor MUST provide to the design team for review and approval throughout a project's life cycle is called a
The correct answer is C. submittal. See the full explanation below for the reasoning.
Question
A document containing information that a contractor MUST provide to the design team for review and approval throughout a project’s life cycle is called a
Options
- Awork breakdown structure (WBS).
- Brequest for information (RFI).
- Csubmittal.
- Dnotice to proceed.
How the community answered
(38 responses)- A8% (3)
- B18% (7)
- C71% (27)
- D3% (1)
Community Discussion