A project schedule is part of a project's

The correct answer is A. scope of work. See the full explanation below for the reasoning.

Question

A project schedule is part of a project’s

Options

  • Ascope of work.
  • Bclose out phase.
  • Ccost estimate.
  • Dschematic design.

How the community answered

(57 responses)
  • A
    74% (42)
  • B
    16% (9)
  • C
    7% (4)
  • D
    4% (2)