A project schedule is part of a project's
The correct answer is A. scope of work. See the full explanation below for the reasoning.
Question
A project schedule is part of a project’s
Options
- Ascope of work.
- Bclose out phase.
- Ccost estimate.
- Dschematic design.
How the community answered
(57 responses)- A74% (42)
- B16% (9)
- C7% (4)
- D4% (2)