BICSI
RCDD-002 · Question #342
The ICT distribution designer discovers a bonding and grounding conflict when reviewing the contract information, provided by the contract administration team, that the stated requirements differ…
The correct answer is A. submit an RFI to the DOR requesting instruction. See the full explanation below for the reasoning.
Question
The ICT distribution designer discovers a bonding and grounding conflict when reviewing the contract information, provided by the contract administration team, that the stated requirements differ from those of the manufacturer, local safety codes and BICSI guidelines. The designer should
Options
- Asubmit an RFI to the DOR requesting instruction.
- Bresolve the issue with the AHJ before proceeding.
- Cfollow the BICSI guidelines.
- Dfollow the manufacturer's recommendation to ensure warranty provisioning.
How the community answered
(29 responses)- A83% (24)
- B7% (2)
- C3% (1)
- D7% (2)
Community Discussion
No community discussion yet for this question.