A program manager notices that one project manager tends to withdraw during important team discussions to avoid conflict. What technique could the program manager use to gam more input from this…
The correct answer is C. Solicit ideas from each team member individually, giving each person a chance to express their. You've hit your session limit · resets 10:20pm (America/New_York)
Question
A program manager notices that one project manager tends to withdraw during important team discussions to avoid conflict. What technique could the program manager use to gam more input from this project manager?
Options
- AInstitute an incentive program to create competition among the team members.
- BMake the project manager share an office with a more assertive team member
- CSolicit ideas from each team member individually, giving each person a chance to express their
- DCreate an online message board so team members can see and respond to everyone's ideas
How the community answered
(34 responses)- A12% (4)
- B6% (2)
- C79% (27)
- D3% (1)
Explanation