RCDD-002 · Question #187
Program manager B leaves the program and program manager A takes over the program responsibilities. Program manager A wants to ensure that all expected benefits of the program are realized. What is…
The correct answer is C. Program business case. See the full explanation below for the reasoning.
Question
Program manager B leaves the program and program manager A takes over the program responsibilities. Program manager A wants to ensure that all expected benefits of the program are realized. What is used to assess the program cost/benefit justification?
Options
- AProgram charter
- BBenefits management plan
- CProgram business case
- DProgram scope statement
How the community answered
(26 responses)- A4% (1)
- B4% (1)
- C77% (20)
- D15% (4)