Question
The chief executive officer (CEO) informs the program manager that the delivery dale for protect A must be compressed by two months to accommodate market needs Project A relies upon deliverables from projects B and C. Which of the following should the program manager do first?
Options
- ADirect the three project managers to crash their projects to allow project A the two months of
- BReview the program resource management plan with the three project managers emphasizing
- CConvene the change board to evaluate the cost benefit of the compression and the impact on the
- DEngage the executive sponsor and program board to evaluate the CEO's request and determine if
Unlock RCDD-002 to see the answer