RCDD-002 · Question #117
A component protect of a multiyear program delivers all expected products and services as anticipated. The component project manager obtains approvals from the stakeholders and transitions the…
The correct answer is A. Reassign the component project manager to another component project or activity. See the full explanation below for the reasoning.
Question
A component protect of a multiyear program delivers all expected products and services as anticipated. The component project manager obtains approvals from the stakeholders and transitions the benefits to operations. What should the program manager do next?
Options
- AReassign the component project manager to another component project or activity
- BVerify that the benefits were delivered and authorize component project closure
- CConduct a program audit to confirm that the component protect is complete
- DKeep the component project open until the program benefits are realized
How the community answered
(55 responses)- A71% (39)
- B16% (9)
- C4% (2)
- D9% (5)