A company's marketing department Tails an internal compliance audit. To comply with the auditor's remediation plan the legal department mandates that a content management system (CMS) be…

The correct answer is B. Host a kick-off meeting, request preliminary requirements from the marketing department. See the full explanation below for the reasoning.

Question

A company's marketing department Tails an internal compliance audit. To comply with the auditor's remediation plan the legal department mandates that a content management system (CMS) be implemented. After initiating the program for CMS implementation the program manager discovers that the marketing department has already preselected which CMS technology will be implemented. What should the program manager do to ensure the success of the program?

Options

  • AMeet with the vice president of purchasing to discuss the risks associated with preselecting a
  • BHost a kick-off meeting, request preliminary requirements from the marketing department,
  • CAsk a senior marketing executive to act as the program sponsor and participate on the steering
  • DInitiate the program and begin a formal request for proposal (RFP) to validate the chosen solution

How the community answered

(49 responses)
  • A
    2% (1)
  • B
    82% (40)
  • C
    4% (2)
  • D
    12% (6)