Which of the following might the Scrum Team discuss during a Sprint Retrospective? (choose the best answer)

The correct answer is E. All of the above. During the Sprint Retrospective, the Scrum Team discusses how the last Sprint went with regards to individuals, interactions, processes, tools, and their Definition of Done123. This includes methods of communication, the way the Scrum Team does Sprint Planning, skills needed to…

Applying Scrum

Question

Which of the following might the Scrum Team discuss during a Sprint Retrospective? (choose the best answer)

Options

  • AMethods of communication.
  • BThe way the Scrum Team does Sprint Planning.
  • CSkills needed to improve the Developers ability to deliver.
  • DThe Definition of Done.
  • EAll of the above.

How the community answered

(48 responses)
  • B
    4% (2)
  • C
    2% (1)
  • D
    6% (3)
  • E
    88% (42)

Explanation

During the Sprint Retrospective, the Scrum Team discusses how the last Sprint went with regards to individuals, interactions, processes, tools, and their Definition of Done123. This includes methods of communication, the way the Scrum Team does Sprint Planning, skills needed to improve the Developers' ability to deliver, and the Definition of Done123.