Question
The IT manager asks a Scrum Team for a status report describing the progress throughout the Sprint. The Scrum Team asks the Scrum Master for advice. The Scrum Master should: (choose the best answer)
Options
- ATell the Developers to fit the report into the Sprint Backlog.
- BAsk the Product Owner to send the manager the report.
- CCreate and deliver the report to the manager herself.
- DTell the Scrum Team to figure it out themselves.
- ETalk to the IT manager and explain that progress in Scrum comes from inspecting an Increment at