PSPO-I · Question #118

What is a Product Owner typically responsible for during a Sprint? (choose the best two answers)

The correct answer is E. Collaborating with stakeholders, users, and customers. F. Working with the Scrum Team on Product Backlog refinement. The Product Owner is typically responsible for collaborating with stakeholders, users, and customers to understand their needs and expectations, and to validate the value of the product. The Product Owner is also responsible for working with the Scrum Team on Product Backlog…

Stakeholders & Customers

Question

What is a Product Owner typically responsible for during a Sprint? (choose the best two answers)

Options

  • AAttending every Daily Scrum to answer questions about the Sprint Backlog
  • BCreating financial reporting upon the spent hours reported by the Developers.
  • CNothing.
  • DUpdating the work plan for the Developers on a daily basis.
  • ECollaborating with stakeholders, users, and customers.
  • FWorking with the Scrum Team on Product Backlog refinement.

How the community answered

(43 responses)
  • B
    2% (1)
  • D
    5% (2)
  • E
    93% (40)

Explanation

The Product Owner is typically responsible for collaborating with stakeholders, users, and customers to understand their needs and expectations, and to validate the value of the product. The Product Owner is also responsible for working with the Scrum Team on Product Backlog refinement, which is the act of adding detail, estimates, and order to Product Backlog items.1 These two responsibilities help the Product Owner to maximize the value of the product and the work of the Developers. 1: The Scrum Guide2, page 18 2: The Scrum Guide

Topics

#Product Owner#stakeholder collaboration#Product Backlog refinement#Sprint

Community Discussion

No community discussion yet for this question.