PSPO-I · Question #88

PSPO-I Question #88: Real Exam Question with Answer & Explanation

Sign in or unlock PSPO-I to reveal the answer and full explanation for question #88. The question stem and answer options stay visible for context.

Question

Several Sprints into a project, the Product Owner tells the Scrum Master that a key stakeholder just started using the product. The stakeholder is unhappy with the quality of the product. What are two good options for the Scrum Master? (choose the best two answers)

Options

  • ACoach the Product Owner on how to talk with the Developers about this
  • BWait to bring this up until the Sprint Retrospective.
  • CExplain to the Product Owner that it is up to the Developers to decide on
  • DEncourage the Product Owner to put quality specifications on the Product
  • EBring the concern to the testers to improve how the Product is verified.

Unlock PSPO-I to see the answer