PSPO-I · Question #33
All Scrum artifacts must be transparent to ensure sufficient accuracy of inspection. Which two measures ensure that the Product Backlog is transparent? (choose the best two answers)
A (ordered) and B (available to all stakeholders) are the two correct measures. Ordering the Product Backlog ensures transparency by making priorities visible and unambiguous - anyone inspecting it can immediately see what is most important and why, which is a core requirement…
Question
All Scrum artifacts must be transparent to ensure sufficient accuracy of inspection. Which two measures ensure that the Product Backlog is transparent? (choose the best two answers)
Options
- AThe Product Backlog is ordered.
- BThe Product Backlog is available to all stakeholders.
- CEach Product Backlog item has a MoSCoW priority.
- DThe Product Backlog only has work for the next 2 Sprints.
- EThe Product Backlog is managed using a web-based tool.
Explanation
A (ordered) and B (available to all stakeholders) are the two correct measures.
Ordering the Product Backlog ensures transparency by making priorities visible and unambiguous - anyone inspecting it can immediately see what is most important and why, which is a core requirement in the Scrum Guide. Availability to all stakeholders satisfies the definition of transparency itself: an artifact is transparent only when those who need to inspect it actually can inspect it. C is wrong because MoSCoW is an external prioritization technique not mentioned in Scrum - Scrum uses ordering, not labeling schemes. D is wrong because the Product Backlog intentionally holds all known future work, not just the next two Sprints; limiting it artificially hides information rather than making it transparent. E is wrong because the tool used to manage the backlog is irrelevant to transparency - a handwritten list shared openly is more transparent than a locked-down Jira board.
Memory tip: Link "transparency" to its two natural requirements - what is in it must be clear (ordered = priorities visible) and who can see it must be everyone (available to stakeholders). If an answer describes a specific tool, a capped scope, or a non-Scrum labeling method, it's a distractor.