PSPO-I · Question #27

PSPO-I Question #27: Real Exam Question with Answer & Explanation

Sign in or unlock PSPO-I to reveal the answer and full explanation for question #27. The question stem and answer options stay visible for context.

Question

You have just been hired by a company new to Scrum. Your management has assigned you to be the Scrum Master of six new Scrum Teams. These teams will build one product. Select two conditions you should strive for in this scenario. (choose the best two answers)

Options

  • AEach Scrum Team should have a separate Product Backlog.
  • BThere should be only one Product Owner.
  • CThe product has one Product Backlog.
  • DThere should be six Product Owners, one for each Scrum Team.
  • EThere should be six Product Owners, reporting to a Chief Product Owner.