nerdexam
Scrum

PSPO-I · Question #22

As the Developers start work during the Sprint, they realize they have selected too much work to finish in the Sprint. What should they do? (choose the best answer)

The correct answer is B. As soon as possible in the Sprint, work with the Product Owner to remove some work or Product. This is the best answer because it respects the Scrum values of openness, commitment, and focus. The Developers should be transparent about their progress and collaborate with the Product Owner to adjust the Sprint scope accordingly. The Product Owner is responsible for…

Applying Scrum

Question

As the Developers start work during the Sprint, they realize they have selected too much work to finish in the Sprint. What should they do? (choose the best answer)

Options

  • AFind another Scrum Team to give the excess work to.
  • BAs soon as possible in the Sprint, work with the Product Owner to remove some work or Product
  • CInform the Product Owner at the Sprint Review, but prior to the demonstration.
  • DReduce the Definition of Done and get all of the Product Backlog items done by the new definition.

How the community answered

(47 responses)
  • A
    4% (2)
  • B
    83% (39)
  • C
    2% (1)
  • D
    11% (5)

Explanation

This is the best answer because it respects the Scrum values of openness, commitment, and focus. The Developers should be transparent about their progress and collaborate with the Product Owner to adjust the Sprint scope accordingly. The Product Owner is responsible for maximizing the value of the product and the work of the Developers, so he or she should be involved in any decisions that affect the Sprint Goal and the Product Backlog. Reference: Scrum Guide, page 10: "If the work turns out to be different than the Developers expected, they collaborate with the Product Owner to negotiate the scope of Sprint Backlog within the Sprint." Scrum Guide, page 11: "The Product Owner is accountable for maximizing the value of the product resulting from the work of the Scrum Team."

Topics

#Sprint planning#scope management#Developer accountability#Product Backlog

Community Discussion

No community discussion yet for this question.

Full PSPO-I Practice