Question

As the Developers start work during the Sprint, they realize they have selected too much work to finish in the Sprint. What should they do? (choose the best answer)

Options

  • AFind another Scrum Team to give the excess work to.
  • BAs soon as possible in the Sprint, work with the Product Owner to remove some work or Product
  • CInform the Product Owner at the Sprint Review, but prior to the demonstration.
  • DReduce the Definition of Done and get all of the Product Backlog items done by the new definition.