PSPO-I · Question #152
Who is accountable for tracking the remaining work toward the Sprint Goal? (choose the best answer)
The correct answer is A. The Developers. The Developers are the ones who are accountable for tracking the remaining work toward the Sprint Goal. The Developers are self-managing and decide how much work they can do in a Sprint1. They also create and update the Sprint Backlog, which is the plan for how the Developers…
Question
Who is accountable for tracking the remaining work toward the Sprint Goal? (choose the best answer)
Options
- AThe Developers.
- BThe Project Manager.
- CThe Product Owner.
- DThe Scrum Master.
How the community answered
(39 responses)- A95% (37)
- C3% (1)
- D3% (1)
Explanation
The Developers are the ones who are accountable for tracking the remaining work toward the Sprint Goal. The Developers are self-managing and decide how much work they can do in a Sprint1. They also create and update the Sprint Backlog, which is the plan for how the Developers will achieve the Sprint Goal, and the single source of truth for the work to be done in the Sprint2. The Developers use the Daily Scrum to inspect their progress toward the Sprint Goal and adapt the Sprint Backlog as necessary[3][3]. The Product Owner, the Scrum Master, and the Project Manager (if any) do not have the accountability for tracking the remaining work toward the Sprint Goal, as this is the responsibility of the Developers. 1: The Scrum Guide, November 2020, p. 6 2: The Scrum Guide, November 2020, p. 10 [3][3]: The Scrum Guide, November 2020, p. 11