Who determines how many Product Backlog items the Developers select for a Sprint? (choose the best answer)
The correct answer is B. The Developers. The Developers are the ones who determine how many Product Backlog items they select for a Sprint. The Developers are self-managing and decide how much work they can do in a Sprint1. The Product Owner and the Developers collaborate on the scope of the Sprint during Sprint…
Question
Who determines how many Product Backlog items the Developers select for a Sprint? (choose the best answer)
Options
- AThe Scrum Team
- BThe Developers.
- CThe Product Owner.
- DThe Scrum Master.
- EThe stakeholders attending Sprint Planning.
How the community answered
(30 responses)- B90% (27)
- D7% (2)
- E3% (1)
Explanation
The Developers are the ones who determine how many Product Backlog items they select for a Sprint. The Developers are self-managing and decide how much work they can do in a Sprint1. The Product Owner and the Developers collaborate on the scope of the Sprint during Sprint Planning, but the final decision is up to the Developers2. The Product Owner, the Scrum Master, and the stakeholders do not have the authority to tell the Developers how many Product Backlog items they should select, as this would violate the principle of self-management[3][3]. 1: The Scrum Guide, November 2020, p. 6 2: The Scrum Guide, November 2020, p. 10 [3][3]: Understanding and Applying the Scrum Framework, Scrum.org, accessed on December 16,