Question

When can Developers cancel a Sprint? (choose the best answer)

Options

  • AWhen functional expectations are not well understood.
  • BWhen the selected Product Backlog items for the Sprint become unachievable.
  • CThey cannot. Only Product Owners can cancel Sprints.
  • DWhen the Product Owner is absent too often.
  • EWhen a technical dependency cannot be resolved.