nerdexam
Scrum

PSPO-I · Question #132

When does the second Sprint start? (choose the best answer)

The correct answer is C. Immediately after the first Sprint. Sprints are fixed-length events of one month or less that serve as a container for the other Scrum events and activities. Sprints have consistent durations throughout a development effort. A new Sprint starts immediately after the conclusion of the previous Sprint. There is no…

Applying Scrum

Question

When does the second Sprint start? (choose the best answer)

Options

  • AAfter the customer completes acceptance testing of the first Sprint.
  • BOnce the architectural changes for the second Sprint are approved by the senior
  • CImmediately after the first Sprint.
  • DAfter the Product Backlog items for the second Sprint have been selected.

How the community answered

(60 responses)
  • A
    5% (3)
  • B
    3% (2)
  • C
    90% (54)
  • D
    2% (1)

Explanation

Sprints are fixed-length events of one month or less that serve as a container for the other Scrum events and activities. Sprints have consistent durations throughout a development effort. A new Sprint starts immediately after the conclusion of the previous Sprint. There is no gap or downtime between Sprints. The second Sprint starts right after the first Sprint, regardless of the customer acceptance testing, the architectural changes, or the Product Backlog items. Understanding and Applying the Scrum Framework Professional Scrum Product Owner™I Certification

Topics

#Sprint timing#Sprint cadence#Scrum events

Community Discussion

No community discussion yet for this question.

Full PSPO-I Practice