PSPO-I · Question #123
When is the Sprint Backlog created? (choose the best answer)
The correct answer is D. During Sprint Planning. The Sprint Backlog is created during Sprint Planning, where the Developers select the Product Backlog items that they can deliver in the Sprint and create a plan for how to do the work. The Scrum Guide states that "The Sprint Backlog is composed of the Sprint Goal (why), the…
Question
When is the Sprint Backlog created? (choose the best answer)
Options
- APrior to Sprint Planning.
- BDuring refinement.
- CDuring the Sprint Retrospective.
- DDuring Sprint Planning.
How the community answered
(21 responses)- B5% (1)
- C5% (1)
- D90% (19)
Explanation
The Sprint Backlog is created during Sprint Planning, where the Developers select the Product Backlog items that they can deliver in the Sprint and create a plan for how to do the work. The Scrum Guide states that "The Sprint Backlog is composed of the Sprint Goal (why), the set of Product Backlog items selected for the Sprint (what), as well as an actionable plan for delivering the Increment (how)."1 The Sprint Backlog is owned and managed by the Developers, who can update it throughout the Sprint as more is learned. 1: The Scrum Guide2, page 15 2: The Scrum Guide
Topics
Community Discussion
No community discussion yet for this question.