nerdexam
Scrum

PSPO-I · Question #114

PSPO-I Question #114: Real Exam Question with Answer & Explanation

The correct answer is C. Each Scrum Team is accountable for developing functionality from beginning to end.. The best approach for Scrum Teams to produce valuable Increments is to be accountable for developing functionality from beginning to end, as this enables them to deliver potentially releasable products that meet the definition of "Done". The Scrum Guide states that "The Developer

Question

Which approach is best for Scrum Teams in order to produce valuable Increments? (choose the best answer)

Options

  • AEach Developer works on the component where they feel that they can contribute.
  • BEach Scrum Team works on an independent set of components.
  • CEach Scrum Team is accountable for developing functionality from beginning to end.
  • DEach Scrum Member works only as an independent layer of the system.

Explanation

The best approach for Scrum Teams to produce valuable Increments is to be accountable for developing functionality from beginning to end, as this enables them to deliver potentially releasable products that meet the definition of "Done". The Scrum Guide states that "The Developers are the people in the Scrum Team that are committed to creating any aspect of a usable Increment each Sprint."1 This means that the Developers are not limited by the boundaries of components, layers, or technologies, but rather they collaborate and coordinate to deliver a complete and integrated product that satisfies the Sprint Goal and the Product Owner's expectations. 1: The Scrum Guide2, page 7 2: The Scrum Guide

Community Discussion

No community discussion yet for this question.

Full PSPO-I Practice